GQL Statement

DIVIDE(
  SUM(
    V(energy_greengas_upgrade_biogas, capital_expenditures_excluding_ccs_per(:plant)),
    V(energy_greengas_upgrade_biogas, operating_expenses_excluding_ccs_per(:plant))
  ),
  V(energy_greengas_upgrade_biogas, typical_input_capacity) * 1000
)

Result

2019 0.74 ms
99.68354430379746
euro
2050 0.06 ms
99.68354430379746
euro

Description

Characteristics

Groups
Unit euro
File path /app/tmp/etsource/gqueries/modules/holon/economy/depreciation_costs_assets/depreciation_costs_energy_greengas_upgrade_biogas_per_kw.gql

References