GQL Statement

estimated_peak_demand_factor = 0.000427;
estimated_peak_demand_factor *
SUM(
  V(Q(time_resolved_heat_network_mt_demand_converters), "input_of_steam_hot_water / MJ_PER_MWH"))

Result

2019 10.9 ms
0.0
MW
2050 10.37 ms
0.0
MW

Description

For the present and if time-resolved calculations are turned off
the hourly input curves are not available. In that case
we estimate peak demand by multiplying total demand (in MWh)
by a 'peak demand factor'. This factor is based on NL2015 dataset by
dividing the future demand peak in a blank scenario by the total demand

Characteristics

Groups
Unit MW
File path /app/tmp/etsource/gqueries/general/costs/heat_infrastructure/mt/general_support_queries/demand_peaks/total_district_heating_mt_demand_peak_estimate.gql

References

Gquery total_district_heating_mt_demand_peak