Present 0 0 0
Future 0 0 0
Edges 0 Outputs
20.0 %
Node MJ Type
energy_production_aggregator_mt_steam_hot_water 0 Flexible
Reversed
80.0 %
Inputs Edges 0
100.0 %
Type MJ Node
Share 0 energy_distribution_wood_pellets
Edges 0 Outputs
20.0 %
Node MJ Type
energy_production_aggregator_mt_steam_hot_water 0 Flexible
Reversed
80.0 %
Inputs Edges 0
100.0 %
Type MJ Node
Share 0 energy_distribution_wood_pellets
Method Label Present Future Unit
technical
heat_output_conversion Heat efficiency (LHV) 80.0 80.0 %
heat_output_capacity Heat capacity per unit 16.7 16.7 MW / unit
full_load_hours Full load hours 2,190 0 hour / year
cost
total_investment_over_lifetime_per(:plant) Investment over lifetime per plant 8,185 K 8,185 K EUR / unit
fixed_operation_and_maintenance_costs_per(:plant) Fixed operation and maintenance costs 433 K 433 K EUR / unit / year
variable_operation_and_maintenance_costs_per(:full_load_hour) Variable operation and maintenance costs 0 NaN EUR / full load hour
wacc Weighted average cost of capital 4.0 4.0 %
takes_part_in_ets Do emissions have to be paid through the ETS? false false boolean
other
technical_lifetime Technical lifetime 15 15 years
Node Attributes Present Future Change Unit
operational
electricity_output_capacity 0 0 MWe
heat_output_capacity 16.7 16.7 0% MWth
hydrogen_output_capacity 0 0 MW
free_co2_factor 0 0
ccs_capture_rate - -
construction_time 2 2 0%
electrical_efficiency_when_using_coal - -
electrical_efficiency_when_using_wood_pellets - -
full_load_hours 2,190 0 -100%
households_supplied_per_unit - -
land_use_per_unit 0 0
takes_part_in_ets 0 0 yes=1 / no=0
technical_lifetime 15 15 0% year
typical_input_capacity - - MWinput
output_capacity - - MW
input_efficiency - -
output_efficiency - -
cost
initial_investment 8,185 K 8,185 K 0% euro / unit
ccs_investment 0 0 euro / unit
cost_of_installing 0 0 euro / unit
decommissioning_costs 0 0 euro / unit
fixed_operation_and_maintenance_costs_per_year 433 K 433 K 0% euro / unit / year
variable_operation_and_maintenance_costs_per_full_load_hour 0 0 euro / full load hour
variable_operation_and_maintenance_costs_for_ccs_per_full_load_hour 0 0 euro / full load hour
fixed_costs_per_mw_input_capacity - - euro / MWinput
costs_per_mj - -
wacc 0.04 0.04 0%
profitability - - profitable / unprofitable / conditionally_profitable
profit_per_mwh_electricity - - eur/MWh
marginal_costs - - euro / MWh
max_consumption_price - - euro / MWh
merit_order
merit_order_full_load_hours - -
merit_order_capacity_factor - -
merit_order_position - -
security_of_supply
availability 1 1 0%
part_load_operating_point - -
part_load_efficiency_penalty - -
forecasting_error - -
misc
demand_expected_value - -
excel_id - -
max_demand - -
Node Calculations Present Future Change Unit
demand
demand 0 0
preset_demand 0 0
demand_of_sustainable 0 0
weighted_carrier_cost_per_mj 0.008 0.008 0%
weighted_carrier_co2_per_mj 0 0
sustainability_share 1 1 0%
final_demand 0 0
primary_demand 0 0
primary_demand_of_fossil 0 0
primary_demand_of_sustainable 0 0
technical
input_capacity 20.87 20.87 0%
electric_based_input_capacity - - MWinput
heat_based_input_capacity 20.87 20.87 0% MWinput
cooling_based_input_capacity - - MWinput
number_of_units 0 0
costs_per_plant
total_costs_per(:plant) 2,534 K 1,165 K -54% euro / plant
fixed_costs_per(:plant) 1,165 K 1,165 K 0%
cost_of_capital_per(:plant) 186 K 186 K 0%
depreciation_costs_per(:plant) 546 K 546 K 0%
variable_costs_per(:plant) 1,369 K 0 -100%
fuel_costs_per(:plant) 1,369 K 0 -100%
co2_emissions_costs_per(:plant) 0 0
captured_biogenic_co2_costs_per(:plant) 0 0
fixed_operation_and_maintenance_costs_per(:plant) 433 K 433 K 0%
variable_operation_and_maintenance_costs_per(:plant) 0 0
total_initial_investment_per(:plant) 8,185 K 8,185 K 0%
costs_per_node
total_costs_per(:node) 0 0
fixed_costs_per(:node) 0 0
cost_of_capital_per(:node) 0 0
depreciation_costs_per(:node) 0 0
variable_costs_per(:node) 0 0
fuel_costs_per(:node) 0 0
co2_emissions_costs_per(:node) 0 0
captured_biogenic_co2_costs_per(:node) 0 0
fixed_operation_and_maintenance_costs_per(:node) 0 0
variable_operation_and_maintenance_costs_per(:node) 0 0
total_initial_investment_per(:node) 0 0
costs_per_mw_electricity
total_costs_per(:mw_electricity) 0 0
fixed_costs_per(:mw_electricity) 0 0
cost_of_capital_per(:mw_electricity) 0 0
depreciation_costs_per(:mw_electricity) 0 0
variable_costs_per(:mw_electricity) 0 NaN
fuel_costs_per(:mw_electricity) 0 NaN
co2_emissions_costs_per(:mw_electricity) NaN NaN
captured_biogenic_co2_costs_per(:mw_electricity) NaN NaN
fixed_operation_and_maintenance_costs_per(:mw_electricity) 0 0
variable_operation_and_maintenance_costs_per(:mw_electricity) NaN NaN
total_initial_investment_per(:mw_electricity) 0 0
costs_per_mwh_electricity
total_costs_per(:mwh_electricity) 0 0
fixed_costs_per(:mwh_electricity) 0 0
cost_of_capital_per(:mwh_electricity) 0 0
depreciation_costs_per(:mwh_electricity) 0 0
variable_costs_per(:mwh_electricity) 0 NaN
fuel_costs_per(:mwh_electricity) 0 NaN
co2_emissions_costs_per(:mwh_electricity) NaN NaN
captured_biogenic_co2_costs_per(:mwh_electricity) NaN NaN
fixed_operation_and_maintenance_costs_per(:mwh_electricity) 0 0
variable_operation_and_maintenance_costs_per(:mwh_electricity) NaN NaN
total_initial_investment_per(:mwh_electricity) 0 0
costs_per_mw_heat
total_costs_per(:mw_heat) 152 K 69,737.2 -54%
fixed_costs_per(:mw_heat) 69,737.2 69,737.2 0%
cost_of_capital_per(:mw_heat) 11,109.3 11,109.3 0%
depreciation_costs_per(:mw_heat) 32,674.5 32,674.5 0%
variable_costs_per(:mw_heat) 82,004.5 0 -100%
fuel_costs_per(:mw_heat) 82,004.5 0 -100%
co2_emissions_costs_per(:mw_heat) 0 0
captured_biogenic_co2_costs_per(:mw_heat) 0 0
fixed_operation_and_maintenance_costs_per(:mw_heat) 25,953.3 25,953.3 0%
variable_operation_and_maintenance_costs_per(:mw_heat) 0 0
total_initial_investment_per(:mw_heat) 490 K 490 K 0%
costs_per_mwh_heat
total_costs_per(:mwh_heat) 69.29 0 -100%
fixed_costs_per(:mwh_heat) 31.84 0 -100%
cost_of_capital_per(:mwh_heat) 5.07 0 -100%
depreciation_costs_per(:mwh_heat) 14.92 0 -100%
variable_costs_per(:mwh_heat) 37.44 NaN
fuel_costs_per(:mwh_heat) 37.44 NaN
co2_emissions_costs_per(:mwh_heat) 0 NaN
captured_biogenic_co2_costs_per(:mwh_heat) 0 NaN
fixed_operation_and_maintenance_costs_per(:mwh_heat) 11.85 0 -100%
variable_operation_and_maintenance_costs_per(:mwh_heat) 0 NaN
total_initial_investment_per(:mwh_heat) 223.8 0 -100%