Present 0 0 -
Future 0 0 -
Edges 0 Outputs
Node kg Type
molecules_distribution_before_transport_co2 0 Flexible
Reversed
Co2
100.0 %
Inputs Edges -
Edges 0 Outputs
Node kg Type
molecules_distribution_before_transport_co2 0 Flexible
Reversed
Co2
100.0 %
Inputs Edges -
Method Label Present Future Unit
technical
input_capacity * full_load_hours * number_of_units Total installed capture capacity 0 0 T_CO2 / year
input_capacity * full_load_hours Capture capacity per unit 999999 999999 T_CO2 / year
full_load_hours Full load hours 8,322 8,322 hour / year
cost
total_initial_investment_per(:plant) Initial investment 1.2 B 1.2 B EUR / unit
fixed_operation_and_maintenance_costs_per(:plant) Fixed operation and maintenance costs 48 M 48 M EUR / unit / year
variable_operation_and_maintenance_costs_per_full_load_hour Variable operation and maintenance costs 0 0 EUR / full load hour
wacc Weighted average cost of capital 7.0 7.0 %
other
technical_lifetime Economic lifetime 25 25 years