GQL Statement
IF(AREA(interconnector_capacity) == 0,
  SUM(
    V(
      Q(electricity_producing_converters),
      "input_capacity * electricity_output_conversion * number_of_units"
    )
  ),
  AREA(interconnector_capacity) * 10
)
Result
| 2019 | 58,500.0 | MW | 
| 2050 | 58,500.0 | MW | 
Description
If there is no interconnection capacity in the start year, the max value is set to the installed electricity production  capacity, else it is set to ten times the start capacity
 
Characteristics
| Groups |  | 
| Unit | MW | 
| File path | /app/tmp/etsource/gqueries/input_elements/max_value/electricity_interconnector_max_capacity.gql | 
References