GQL Statement

IF(
    AREA(lv_mv_trafo_spare_capacity) >= 1.0,
    0.0,
    QUERY_PRESENT(lv_mv_trafo_peak_load_present) / (1.0 - AREA(lv_mv_trafo_spare_capacity))
  )

Result

2019 196.53 ms
14,752.883446395323
MW
2050 0.04 ms
14,752.883446395323
MW

Description

The capacity of the the low voltage net in the present. The 0.000001 is to prevent it from breaking, when spare capacity is 100%.

Characteristics

Groups
Unit MW
File path /app/tmp/etsource/gqueries/modules/network_calculation/lv_mv_trafo/capacity/lv_mv_trafo_capacity_present.gql

References

Gquery lv_mv_trafo_capacity_delta_present_future
Gquery lv_mv_trafo_capacity_future
Gquery lv_mv_trafo_extra_capacity_needed