heat_infrastructure_ht_distribution_stations_capital_costs debug
GQL Statement
PRODUCT(
DIVIDE(
Q(heat_infrastructure_ht_distribution_stations_investment_costs),
2.0),
Q(heat_infrastructure_ht_distribution_stations_wacc)
)
Result
| 2019 |
9,959,667.534373911
|
euro |
| 2050 |
9,216,928.495966423
|
euro |
Description
Assuming linear depreciation, in line with ETM cost calculation
Characteristics
| Groups | |
| Unit | euro |
| File path |
/app/tmp/etsource/gqueries/general/costs/heat_infrastructure/ht/distribution_stations_annualised_costs/support_queries/heat_infrastructure_ht_distribution_stations_capital_costs.gql
|
References
| Gquery | heat_infrastructure_ht_distribution_stations_capex |
| Gquery | households_ht_distribution_stations_capex |