energy_power_supercritical_coal
Present
107.45 B
107.45 B
107.45 B
Future
152.31 B
152.31 B
152.31 B
41.75%
|
|
|
|
Details
Node Summary
Method | Label | Present | Future | Unit |
---|---|---|---|---|
technical | ||||
electricity_output_capacity * number_of_units | Installed electrical capacity | 1,953.6 | 1,953.6 | MW |
electricity_output_conversion | Electrical efficiency | 36.0 | 36.0 | % |
full_load_hours | Full load hours | 5,500 | 7,796.4 | hour / year |
cost | ||||
total_investment_over_lifetime_per(:mw_electricity) | Investment over lifetime per MW | 987500 | 987500 | EUR / MW |
fixed_operation_and_maintenance_costs_per(:mw_electricity) | Fixed operation and maintenance costs | 24268 | 24268 | EUR / MW / year |
variable_operation_and_maintenance_costs_per_full_load_hour | Variable operation and maintenance costs | 1580 | 1580 | EUR / full load hour |
wacc | Weighted average cost of capital | 4.0 | 4.0 | % |
takes_part_in_ets | Do emissions have to be paid through the ETS? | true | true | boolean |
other | ||||
technical_lifetime | Technical lifetime | 45 | 45 | years |
All Attributes
Node Attributes | Present | Future | Change | Unit |
---|---|---|---|---|
operational | ||||
electricity_output_capacity | 800 | 800 | 0% | MWe |
heat_output_capacity | 0 | 0 | MWth | |
hydrogen_output_capacity | 0 | 0 | MW | |
free_co2_factor | 0 | 0 | ||
ccs_capture_rate | - | - | ||
construction_time | 4 | 4 | 0% | |
electrical_efficiency_when_using_coal | - | - | ||
electrical_efficiency_when_using_wood_pellets | - | - | ||
full_load_hours | 5,500 | 7,796.4 | 41% | |
households_supplied_per_unit | - | - | ||
land_use_per_unit | 0.3 | 0.3 | 0% | |
takes_part_in_ets | 1 | 1 | 0% | yes=1 / no=0 |
technical_lifetime | 45 | 45 | 0% | year |
typical_input_capacity | - | - | MWinput | |
output_capacity | - | - | MW | |
input_efficiency | - | - | ||
output_efficiency | - | - | ||
cost | ||||
initial_investment | 790 M | 790 M | 0% | euro / unit |
ccs_investment | 0 | 0 | euro / unit | |
cost_of_installing | 0 | 0 | euro / unit | |
decommissioning_costs | 0 | 0 | euro / unit | |
fixed_operation_and_maintenance_costs_per_year | 19.41 M | 19.41 M | 0% | euro / unit / year |
variable_operation_and_maintenance_costs_per_full_load_hour | 1,580 | 1,580 | 0% | euro / full load hour |
variable_operation_and_maintenance_costs_for_ccs_per_full_load_hour | 0 | 0 | euro / full load hour | |
fixed_costs_per_mw_input_capacity | - | - | euro / MWinput | |
costs_per_mj | - | - | ||
wacc | 0.04 | 0.04 | 0% | |
profitability | - | profitable / unprofitable / conditionally_profitable | ||
profit_per_mwh_electricity | - | -5.1 | eur/MWh | |
marginal_costs | 29.97 | 29.97 | 0% | euro / MWh |
max_consumption_price | 29.97 | 29.97 | 0% | euro / MWh |
merit_order | ||||
merit_order_full_load_hours | - | - | ||
merit_order_capacity_factor | - | - | ||
merit_order_position | - | 9 | ||
security_of_supply | ||||
availability | 0.89 | 0.89 | 0% | |
part_load_operating_point | 0.7 | 0.7 | 0% | |
part_load_efficiency_penalty | 0.018 | 0.018 | 0% | |
forecasting_error | 0 | 0 | ||
misc | ||||
demand_expected_value | - | - | ||
excel_id | - | - | ||
max_demand | - | - |